Author Archives: NVR Wagon Group

16/01/24 – One out and one in

As a bit of an impromptu session, Tim, Paul, and Steve, headed to Wansford determined to achieve some more vac fitting. The first job was to get another vacuum cylinder overhauled, so whilst Steve and Paul collected the necessary bits … Continue reading

Posted in Uncategorized | Comments Off on 16/01/24 – One out and one in

13/01/24 – On a roll

Another great turnout saw more progress at Wansford with the vac fitting. The ‘A-Team’ were kept busy overhauling cylinders in the shed, whilst the ‘B-Team’ were outside dropping cylinders off the remaining vans that still have cylinders under. There were … Continue reading

Posted in Uncategorized | 1 Comment

Suck it and see

A slightly late update covering the work carried out on Saturday 30th December by the group…. There was a good turnout at Wansford to continue with the vac fitting of the vehicles that are currently in Wansford Yard. We formed … Continue reading

Posted in Uncategorized | Comments Off on Suck it and see

16/12/23 – Back on vac

(Apologies that this update is out of sequence!) Work started on the three vans shunted in to Wansford yard for attention to the vacuum braking systems. By the end of the session, two cylinders had been removed and moved to … Continue reading

Posted in Uncategorized | Comments Off on 16/12/23 – Back on vac

18/12/23 – With a little help from our friends…

Tim & Steve put in an extra weekday session swapping cylinders on the wagons which had been shunted in to the yard at Wansford as part of the XP Freight project to vac fit the rake, but not before some … Continue reading

Posted in Uncategorized | Comments Off on 18/12/23 – With a little help from our friends…

03/12/23 – Little steps.

A few little tasks knocked off the list this week. Continue reading

Posted in Uncategorized | Comments Off on 03/12/23 – Little steps.

25/11/23 – Component overhauls

Component overhauls in preparation of next week’s work session. Continue reading

Posted in Uncategorized | Comments Off on 25/11/23 – Component overhauls

18/11/23 – Having a Brake

We make a start at the reinstatement of the Vacuum brake system on our Vans and Conflat within the “serviceable” freight set. Continue reading

Posted in Uncategorized | Comments Off on 18/11/23 – Having a Brake

05/11/23 – Calm after the storm

Just a brief update this week after the success of our charter. With a few little but none the less important jobs carried out. Continue reading

Posted in Uncategorized | Comments Off on 05/11/23 – Calm after the storm

29/10/23 – Final week of preparation.

The Boston Bucket Bash is complete, we certainly had a great day and hope the participants did too. Our final days of prep is covered by this update… Continue reading

Posted in Uncategorized | Comments Off on 29/10/23 – Final week of preparation.

22/10/23 – Charter fast approaching.

It’s all coming together for our charter on the 30th, 3 vehicles now returned to traffic. Continue reading

Posted in Uncategorized | Comments Off on 22/10/23 – Charter fast approaching.

15/10/23 – Charter prep.

Charter prep this week as we draw ever closer to the date of the event. With 68070 returning from the scrap yard. Continue reading

Posted in Uncategorized | Comments Off on 15/10/23 – Charter prep.